Re: Planned Orders split per 24h max during MRP Run

$
0
0

Hello Michael

 

You can define a maximum lot sizing procedure and a takt time of 1 day on the material master (tab MRP 1).

 

With this setting, when the maximum lot size is exceeded, a new planned order on the previous day is created.


Regards
Caetano