There are several business reason why you could need to have an overlapping between two operations: for example, the second operation can be started even when the first operation has not been completed.
The overlapping is maintained in the routing (CA02). Click twice in the operation and you will find the Overlapping indicator. Flag this indicator and enter the overlap time and ahead quantity.