Component Version Mismatch problem - Affected Urgent Change

$
0
0

Hi Experts,

 

There is a component version mismatch and due to this in an urgent change transports are not getting imported into test system on status change. As a result status change fails (To Be Tested) and resets back to 'In Development'.

 

So to import transport into test system import option 'Ignore invalid component version' needed to choose for each urgent change. Is there any way to automate transport import into test system (for urgent change only) having component version mismatch problem.

 

Br,

Omkar